Nutrien Lanigan Piping Service Tunnel- 2021

Scope: Removal of dead lines throughout the tunnel ranging in size from 3”-6”. Asbestos lines included in scope. Approximately 1165 ft of lines removed. Replacement of asbestos sewage lines, steel sewage lines and fire line. Pipe ranged from 4” to 12”. Approximately 2800 ft of pipe replaced.

Project schedule duration: 9 Months

​